Project Name Scheduled Completion Date Current Status
Student Center Chiller Replacement 5/15/08 Substantial Completion Inspection will be held 3/15/08
Campus Fire Systems 4/30/08 In process
Campus Master Plan 7/08 Meetings with consultants continue
Campus Utility Master Plan 8/08 Consultants are running models
ADA Accessibility Issues 6/30/08 Contractor selected. Velocity Construction, Inc. - On Schedule
Library/Centrum/ Eng. Tech. Concrete Settlement & Water Damage 6/08 Contractor selected. Dual-A Construction - On Schedule
Multipurpose Success Academy Remodel 8/08 Construction has started - Carter Enterprises selected as contractor.
Old Main Remodel 2/08 100% Complete
Teacher Education 2/08 99% Complete
Carter Carillon/Bell Tower 2/08 99% Complete
Science Center Addition Programming 1/08 Programming is complete
Abatement Beverly Ford Home, Steve Alder Home, 2nd Floor of ELC and Terrace area ceiling 5/23/08 Project will begin 5/1/08
Energy Projects
Project Name Scheduled Completion Date Current Status
Recommissioning Sharwan Smith Center 7/08 100% Complete
Recommissioning Student Center 7/08 100% Complete
Recommissioning Centrum 7/08 100% Complete

Report an Error on this Page

Got a Question?

Last Update: Tuesday, April 15, 2008



Note: This site is accessible to any browser, although, it will look much better in a browser that supports web standards.
To view this page properly, please upgrade your browser. We recommend:
Mozilla Firefox (PC/Mac/Linux download)
Opera (PC/Mac/Linux/Solaris download)
Safari (Mac download)